$20 million renovation project to convert a 64,900 sf warehouse to an operations, intel, and cyber warfare facility
Mission Critical Facility
LEED Silver design requirements
Geothermal loop field designed to provide the heat sink for condenser water and a cooling tower installed for additional cooling
Energy recovery wheel installed to extract thermal energy from the exhaust air
Stand-alone early warning detection system for rooms with sensitive electronic equipment
While photo voltaic and solar hot water systems were considered, a ground source heat pump provides the best renewable energy
“Red” power provided to the secure perimeter areas through a 480-volt triple faraday shielded isolation transformer
Design included proper spacing for classified and unclassified communication systems